Garden Surveyor logoGarden Surveyor

Garden Room / Shed Base Calculator

Concrete, timber, gravel grid, paving or ground screw bases.

Inputs

Habitable / heated rooms need a thicker slab (150 mm), insulation and building-regs sign-off.

Drives default depth, mix grade and mesh recommendation.

10 advanced inputs hidden. Switch to Advanced to fine-tune.

Confidencehigh· 81Complexitymedium· 42
Base area
15
Perimeter m
16m
Base type
concrete
MOT Type 1
3.94t
Concrete purpose
garden-room
Mix grade
C25
Reinforcement
A142
Concrete depth
100mm
Concrete volume (incl. waste)
1.58
Wastage Pct
5%
Supply route
site-mix
Cement bags (25 kg)
21kg
Sharp sand
1.34t
20 mm aggregate
2.05t
Mesh sheets (3.6 × 2.0 m)
3
Mesh grade
A142
DPM (1200 g polythene)
18
Formwork (lineal m)
16m
Saw-cut control joints
3
Max joint spacing
2.4m
Wheelbarrow loads (~70 L each)
23
Concrete
1.58
DPM (damp-proof membrane)
18

Heads-up: Base type drives everything else. Concrete is overkill for a light shed; a heavy garden room or hot tub needs concrete or ground screws — gravel grid will sink unevenly under point loads. Why it matters: Match the base to the load: a 2-tonne hot tub on paving slabs will crack the slabs and the joints.

Concrete pour plan
1.6

One continuous pour — line up delivery, access and crew before the truck books in.

Delivery route

Volumetric mini-mix truck

Pump

No pump needed

Crew

2 people — one placing, one tamping & floating.

Why: No pump needed — the truck chute plus a short 15 m barrow run reaches the pour.

Place and level within ~2 hours of delivery; first floating once the surface sheen has gone.

Pour timeline

  1. 1. Before the truck arrives

    Formwork fixed and braced, sub-base compacted and dampened, DPM/reinforcement in place, and the discharge point agreed. Have all hands and finishing tools ready.

  2. 2. Delivery

    Volumetric mini-mix truck backs up to within chute reach.

  3. 3. Pour & level

    Place 1.6 m³ working away from the far edge back to the exit. 2 people — one placing, one tamping & floating. Screed level off the form rails as you go.

  4. 4. Tamp & finish

    Tamp to compact and bring up the laitance, then float to the spec finish. Place and level within ~2 hours of delivery; first floating once the surface sheen has gone.

  5. 5. Joints

    Form or saw-cut 3 control joints — saw-cutting is done within 6–24 h while the slab is green to control cracking.

  6. 6. Cure

    Keep covered and damp (or use a curing compound) for at least 3 days; reaches ~70% strength in 7 days and full design strength at 28 days. Don't load before then.

This app provides general UK guidance and material estimates only. It is not legal, planning, engineering or building-control advice. Always confirm requirements with your local planning authority, building control, utility providers, manufacturers or qualified professionals.